Project
|
Status
|
Budget
|
Construction
|
Project Number |
Title |
Phase |
Phase % Complete |
Bldg. |
Pic. |
Project Manager |
Assistant Director |
Project |
Const. |
Expenses -to-date |
Start |
Finish |
|
|
|
|
| 18132A | ALBANY VILLAGE - REAL ESTATE | Study Only | % | | | HUFFERD | MARTHINSEN | 168,500 | 0 | 2,516,775 | | |
| 12810A | University Village Redevelopme | Construction | 99% | |  | MAR | GAYLE | 110,242,373 | 94,071,654 | 106,881,610 | 09/01/2004 | 07/29/2008 |
| 12040A | STANLEY HALL REPLACEMENT | Closeout | 80% | Stanley |  | DIXON | BLUHM | 140,296,000 | 111,757,988 | 140,045,114 | 02/03/2003 | 04/02/2007 |
| 12115A | DAVIS HALL NORTH REPLACEMENT | Construction | 83% | Davis |  | FEHER | GAYLE | 176,830,000 | 142,632,000 | 136,048,555 | 05/24/2006 | 01/13/2009 |
| 12030B | TOLMAN HALL - Seismic Correcti | Study Only | % | Tolman | | PALMER | BLUHM | 250,000 | 0 | 2,830 | | |
| 12623D | HMMB - EQUIPMENT | Closeout | 99% | HMMB | | FEHER | GAYLE | 3,150,000 | 2,100,000 | 3,132,712 | 07/01/2002 | 01/13/2006 |
| 17433A | CAMPUS GROUND-SAFETY LIGHTING | Construction | 95% | Landscape - Cam | | HORNER | GAYLE | 240,000 | 155,000 | 208,537 | 08/01/2006 | 08/27/2008 |
| 19335A | RFS Remediation & Restoration | Construction | 50% | Richmond Field | | FUNG | JOHNSON | 32,358,041 | 12,258,041 | 15,844,396 | 09/11/2002 | 12/31/2012 |
| 12176A | EAST ASIAN LIBRARY BUILDING | Closeout | 90% | East Asian Libr |  | MATHERS | GAYLE | 46,400,000 | 33,731,843 | 45,503,333 | 08/24/2005 | 10/23/2007 |
| 12017A | Campbell Hall Seismic Replacem | Working Drawings | 50% | Campbell | | ROSENTHAL | BLUHM | 73,311,000 | 54,311,000 | 2,455,170 | 10/01/2009 | 07/30/2012 |
| 12623M | HMMB Management | Closeout | 90% | Hearst Min | | GAYLE | GAYLE | 2,700,000 | 503,000 | 2,680,537 | | |
| 17517A | ICCS Step 5 | Closeout | 100% | | | TOWN | JOHNSON | 295,000 | 190,000 | 296,800 | 04/01/2004 | 08/01/2004 |
| 12211A | Birge Hall Ground Floor Renova | Construction | 95% | Birge | | PIANCA | ZILBER | 1,600,000 | 1,102,186 | 1,487,841 | 08/01/2004 | 12/31/2007 |
| 12699A | Doe Library Annex Seismic Corr | Construction | 99% | Doe Annex |  | MAR | GAYLE | 55,205,000 | 43,285,000 | 51,242,620 | 04/17/2006 | 05/25/2008 |
| 12202A | LeConte Hall Program Improveme | Closeout | 50% | Le Conte | | MACARDLE | BLUHM | 13,643,000 | 11,100,000 | 12,719,119 | 07/18/2005 | 09/29/2006 |
| 17557A | Baker Forest Computer Lab Buil | Construction | 90% | | | OWENS | ZILBER | 242,000 | 90,000 | 181,782 | 05/15/2005 | 09/15/2008 |
| 12221A | Underhill Field and Parking Re | Closeout | 100% | Underhill Parki |  | TOWN | JOHNSON | 42,667,000 | 34,060,500 | 39,852,177 | 09/01/2005 | 08/27/2007 |
| 12225A | Birge Hall Riser Upgrade | Bid/Award | 100% | Birge | | GEE | ZILBER | 599,000 | 459,000 | 122,116 | | |
| 12237A | Relocate Campus Data Center Fr | Bid/Award | 50% | Bechtel Cntr | | TOWN | JOHNSON | 300,000 | 0 | 796,926 | | 03/01/2009 |
| 12238A | North Central Utilities Projec | Bid/Award | 80% | Landscape - Cam | | HORNER | GAYLE | 3,044,327 | 2,563,327 | 2,532,453 | 03/23/2005 | 11/28/2008 |
| 12231A | 2111 Bancroft Seismic Correcti | Working Drawings | 100% | Bancroft 2111 | | DANIELS | ZILBER | 1,652,000 | 0 | 347,294 | | |
| 12232A | MLK Student Union Seismic Corr | Working Drawings | 60% | King Union | | PETERSON | ZILBER | 7,900,000 | 6,250,000 | 748,133 | 02/02/2009 | 09/30/2009 |
| 12040C | Stanley Hall QB3 Fit Up | Closeout | 100% | Stanley | | STENBERG | BLUHM | 1,115,000 | 300,000 | 976,840 | 11/01/2005 | 01/31/2008 |
| 12040D | Stanley Hall Furniture, Fit Up | Construction | 98% | Stanley |  | STENBERG | BLUHM | 5,750,000 | 1,610,350 | 5,170,044 | 11/01/2005 | 01/30/2009 |
| 12040E | Stanley Hall Cafe Fit Up | Closeout | 50% | Stanley | | ZYLLA | JOHNSON | 507,599 | 60,000 | 399,105 | 05/05/2008 | 07/25/2008 |
| 18193A | Physical Sciences Improvements | Study Only | 95% | Campbell | | ROSENTHAL | BLUHM | 200,000 | 0 | 170,875 | | |
| 17616A | Campus Accessibility Improveme | Working Drawings | 100% | | | HORNER | GAYLE | 345,000 | 240,000 | 338,089 | 05/30/2006 | 04/29/2008 |
| 12259A | Downtown UCB Art Museum/Pacifi | Schematic Design | 100% | Downtown UCB Ar | | CHUNG | GAYLE | 7,877,023 | 0 | 6,658,828 | 04/26/2010 | 10/19/2012 |
| 12257A | Hildebrand Hall Rooms 403A & 4 | Closeout | 100% | Hildebrand |  | FUNG | BLUHM | 2,300,000 | 1,795,000 | 2,209,080 | 05/16/2007 | 12/14/2007 |
| 12255A | LeConte Hall Room 375 Renovati | Construction | 85% | Le Conte | | BRADSHAW | BLUHM | 492,500 | 370,000 | 422,265 | 06/01/2007 | 12/31/2008 |
| 18184B | HEARST GYMNASIUM -PHASE 3 VISI | Feasibility | 99% | Hearst Gym | | MARTHINSEN | MARTHINSEN | 470,000 | 0 | 391,237 | | 04/16/2007 |
| 17617A | Campus Accessibility Improveme | Closeout | 1% | | | LEE | ZILBER | 90,000 | 0 | 87,846 | 05/01/2008 | 09/30/2008 |
| 18196A | SE Campus Integrated Projects | Study Only | 0% | | | LAWRENCE | MARTHINSEN | 800,000 | 0 | 836,318 | | |
| 19806A | 2000 Carleton Fire Alarm Repla | Bid/Award | 10% | Carlton2000 | | BRADSHAW | ZILBER | 411,000 | 345,000 | 64,851 | 10/13/2008 | 01/30/2009 |
| 19801A | OBrien Hall Roof Replacement | Closeout | 100% | O'brien | | CHUNG | ZILBER | 492,500 | 285,440 | 465,486 | 03/03/2008 | 08/31/2008 |
| 19804A | Giannini Hall Dormer Decks Res | Closeout | 100% | Giannini | | DANIELS | ZILBER | 1,157,500 | 943,424 | 1,156,468 | 08/14/2006 | 09/15/2007 |
| 19809A | Giannini Hall Exterior Wall Re | Closeout | 100% | Giannini | | DANIELS | ZILBER | 250,000 | 110,000 | 212,206 | 05/21/2007 | 07/20/2007 |
| 19808A | Wurster Hall Windows Restorati | Closeout | 100% | Wurster | | CHUNG | ZILBER | 290,000 | 0 | 281,301 | 12/21/2006 | 07/13/2007 |
| 19810A | Doe Library Window Wall Replac | Closeout | 100% | Doe Library | | CHUNG | ZILBER | 150,000 | 0 | 146,450 | 04/23/2007 | 10/24/2007 |
| 19807A | Evans Hall Elevator 4 & 5 Rest | Closeout | 50% | Evans | | DANIELS | ZILBER | 735,000 | 600,000 | 637,698 | 05/21/2007 | 02/21/2008 |
| 18531A | University Village Albany Reta | Study Only | 0% | | | HUFFERD | MARTHINSEN | 720,000 | 0 | 220,445 | | |
| 12240A | Student Athlete High Performan | Bid/Award | 5% | Stadium | | DIXON | GAYLE | 111,948,000 | 91,182,000 | 9,664,361 | 02/01/2009 | 04/01/2012 |
| 12263A | California Memorial Stadium Se | Schematic Design | 75% | Stadium | | MAR | GAYLE | 0 | 0 | 5,150,381 | | |
| 12265B | Maxwell Field Parking Study | Study Only | 100% | Kleeberger Rr | | DIXON | GAYLE | 0 | 0 | 383,402 | | |
| 17606A | Birge Hall Rooms 159 & 161 Ren | Construction | 98% | Birge | | PIANCA | | 98,000 | 57,000 | 62,167 | 04/10/2006 | 11/30/2007 |
| 12260A | Durant Hall Renovation | Bid/Award | 75% | Durant | | MCGARRAHAN | JOHNSON | 9,970,000 | 8,061,000 | 1,177,794 | 09/01/2008 | 08/28/2009 |
| 12266A | Wellman Courtyard MRI Modular | Closeout | 100% | Wellman Tlrs |  | FUNG | BLUHM | 1,300,000 | 0 | 1,233,451 | 10/08/2007 | 02/21/2008 |
| 12699C | Doe Library Seismic Correction | Construction | 99% | Doe Annex | | MAR | GAYLE | 200,000 | 0 | 153,419 | 04/17/2006 | 05/25/2008 |
| 12269A | C V Starr East Asian Library F | Closeout | 90% | East Asian Libr | | MATHERS | GAYLE | 5,000,000 | 3,970,000 | 4,733,465 | 08/24/2005 | 10/23/2007 |
| 12291A | 2150 Shattuck Leasehold Improv | Closeout | 100% | | | CHUNG | ZILBER | 875,000 | 577,264 | 867,241 | 10/09/2006 | 04/01/2007 |
| 12292A | Warren Surge: Hildebrand PH Fa | Closeout | 100% | Hildebrand | | FUNG | BLUHM | 760,000 | 550,000 | 742,889 | 06/18/2007 | 08/16/2007 |
| 12292B | Warren Surge: Koshland PH Facu | Closeout | 10% | Koshland | | FISH | BLUHM | 485,000 | 176,678 | 441,735 | 07/09/2007 | 04/01/2008 |
| 18199A | Electrical Switchstation 6 Stu | Study Only | 100% | | | TOWN | JOHNSON | 50,000 | 0 | 44,295 | | |
| 19307A | Centennial Drive Landslide Rep | Construction | 100% | | | TOWN | JOHNSON | 1,127,000 | 839,000 | 924,527 | 10/30/2006 | 12/29/2006 |
| 12178A | Central Dining &Office Facilit | Closeout | 100% | Central Dining | | TOWN | JOHNSON | 880,000 | 805,000 | 861,261 | 06/19/2006 | 10/30/2007 |
| 12295A | Mining Circle Historic Renovat | Construction | 96% | Landscape - Cam |  | HORNER | GAYLE | 533,750 | 285,000 | 502,582 | 06/04/2007 | 01/15/2008 |
| 19343A | LeConte Hall Moving Back | Construction | 79% | Le Conte | | CARAVES | ZILBER | 1,050,000 | 191,022 | 587,214 | 07/24/2006 | 01/30/2009 |
| 12291B | 2168 Shattuck Leasehold Improv | Closeout | 100%% | | | CHUNG | ZILBER | 570,000 | 238,211 | 540,959 | 10/16/2006 | 04/01/2007 |
| 19344A | Faculty Club Trellis Replaceme | Closeout | 10% | Faculty Club | | MCGARRAHAN | ZILBER | 117,200 | 67,200 | 115,813 | 09/18/2006 | 12/20/2007 |
| 17622A | Campus Accessibility Improveme | Construction | 80% | | | LEE | ZILBER | 135,000 | 120,000 | 128,454 | 10/02/2006 | 08/29/2008 |
| 17639A | Centennial Drive Pathway Repai | Working Drawings | 60% | Landscape - Cam | | HORNER | GAYLE | 250,000 | 169,000 | 53,493 | 05/03/2008 | 10/24/2008 |
| 19811A | LSA Water Intrusion Remediatio | Closeout | 100% | Lsb Addition |  | DANIELS | ZILBER | 550,000 | 0 | 537,324 | 05/29/2007 | 08/26/2007 |
| 19342A | 2150 & 2168 Shattuck Leases | Closeout | 90% | Shattuk2150 | | CHUNG | GAYLE | 1,347,300 | 0 | 66,321 | 09/11/2006 | |
| 12202D | LeConte Hall Landscape | Construction | 10% | Le Conte | | HORNER | GAYLE | 100,000 | 75,000 | 22,723 | 09/15/2008 | 12/05/2008 |
| 17621A | Strawberry Creek Accessible Cr | Working Drawings | 10% | Landscape - Cam | | HORNER | GAYLE | 300,000 | 196,000 | 41,922 | 10/15/2008 | 12/15/2008 |
| 18203A | Sproul Hall Electrical Distrib | Study Only | 95% | Sproul | | GEE | ZILBER | 40,000 | 0 | 38,391 | | |
| 12249A | Birge Hall Infrastructure Impr | Bid/Award | 95% | Birge | | PIANCA | ZILBER | 10,350,000 | 8,500,000 | 903,368 | 08/08/2008 | 09/30/2009 |
| 12298A | International House Water Line | Bid/Award | 5% | I House | | DIXON | GAYLE | 1,352,624 | 1,098,785 | 177,791 | 12/01/2008 | 08/01/2009 |
| 12302A | Memorial Stadium Offsite Utili | Schematic Design | 20% | Stadium | | DIXON | GAYLE | 0 | 0 | 4,758 | 02/01/2009 | 02/01/2011 |
| 17657A | Lower Jordan Fire Trail Culver | Closeout | 100% | | | TOWN | JOHNSON | 64,000 | 54,000 | 59,283 | 10/25/2006 | 10/01/2007 |
| 12303A | 2151 Berkeley Way Phase One Se | Construction | 95% | 2151 Berkeley W | | ELLISEN | JOHNSON | 574,000 | 428,630 | 568,181 | 12/01/2006 | 10/31/2009 |
| 17656A | 2111 Bancroft Way Career Cente | Construction | 99% | Bancroft 2111 |  | LEONY | JOHNSON | 255,000 | 185,000 | 384,973 | 03/19/2007 | 12/31/2007 |
| 17654A | Moffitt Library Newspaper Disp | Construction | 98% | Moffitt | | HORNER | GAYLE | 150,000 | 120,000 | 136,146 | 03/19/2007 | 04/02/2007 |
| 12294B | University Hall Second Floor a | Closeout | 90% | University |  | LEONY | ZILBER | 1,218,000 | 502,000 | 1,190,562 | 05/14/2007 | 08/10/2007 |
| 12311A | Calvin Lab Improvements for En | Construction | 99% | Calvin Lab |  | FISH | ZILBER | 4,500,000 | 1,500,000 | 3,833,054 | 05/21/2007 | 02/29/2008 |
| 12297A | Sproul Hall Rms 37 & 39 UCPD O | Closeout | 100% | Sproul | | LEFFLER | JOHNSON | 1,289,000 | 960,000 | 1,243,117 | 02/19/2007 | 08/10/2007 |
| 12306A | Law School Building Rooms 100, | Closeout | 100% | Law | | LEFFLER | JOHNSON | 2,000,000 | 785,000 | 1,970,968 | 05/21/2007 | 09/01/2007 |
| 17652A | Le Conte Hall lab restoration | Construction | 95% | Le Conte | | CARAVES | ZILBER | 310,000 | 265,605 | 305,432 | 10/24/2006 | 09/30/2008 |
| 12699D | Doe Library Seismic Correction | Bid/Award | 90% | Doe Annex | | MAR | GAYLE | 4,262,000 | 3,844,910 | 872,021 | 05/19/2008 | 08/15/2008 |
| 19815A | Moses Hall - Slate Tile Roof R | Closeout | 100% | Moses |  | DANIELS | ZILBER | 310,000 | 0 | 225,619 | 08/20/2007 | 10/10/2007 |
| 19817A | Cory Hall - Roof Restoration | Closeout | 100% | Cory |  | OWENS | ZILBER | 1,322,000 | 0 | 1,218,481 | 07/16/2007 | 10/15/2007 |
| 12700A | Doe Library Build-Out & Prepar | Construction | 99% | Doe Annex | | MAR | GAYLE | 4,262,000 | 3,844,413 | 4,097,502 | 02/07/2007 | 05/25/2008 |
| 12312B | Gill Tract - Hazadous Material | Closeout | 100% | Gill Tract Trac | | ELLISEN | ZILBER | 162,000 | 0 | 160,682 | 09/17/2007 | 10/31/2008 |
| 19812A | University Hall - Hot Water Ex | Closeout | 100% | University | | ELLISEN | ZILBER | 165,000 | 30,000 | 140,578 | 12/17/2007 | |
| 19814A | Giannini Fire Alarm Replacemen | Closeout | 100% | Giannini | | ELLISEN | ZILBER | 530,000 | 0 | 395,391 | 09/12/2007 | 01/15/2008 |
| 19813A | O Brien Window and Wall Repair | Construction | 100% | O'brien | | DANIELS | ZILBER | 400,000 | 348,000 | 118,241 | 02/01/2007 | 05/31/2007 |
| 12305A | Wheeler & Barrows Halls Classr | Construction | 98% | Wheeler | | LEE | ZILBER | 1,000,000 | 700,000 | 986,042 | 03/01/2007 | 12/31/2007 |
| 19819A | Sather Tower Exterior Restorat | Bid/Award | 70% | Sather Tower | | ZYLLA | JOHNSON | 360,000 | 40,000 | 65,977 | | |
| 19818A | Replace HV Feed to Strawberry | Construction | 75% | Strawb Feed | | ELLISEN | ZILBER | 400,000 | 0 | 160,746 | 01/15/2008 | 07/01/2009 |
| 17623A | McCone/Hess Halls Entracne Ram | Closeout | 1% | Mccone | | LEE | ZILBER | 130,000 | 0 | 129,529 | 11/30/2007 | 03/31/2008 |
| 17665A | HHMI Renovations for Shared La | Closeout | 75% | Stanley | | DIXON | BLUHM | 336,168 | 240,000 | 286,177 | 02/15/2007 | 03/31/2008 |
| 17666A | HHMI Doudna Lab Modifications | Closeout | 80% | Stanley Annx | | DIXON | BLUHM | 204,453 | 146,000 | 165,567 | 02/15/2007 | 06/30/2008 |
| 17667A | HHMI Kuriyan Lab Modifications | Closeout | 80% | Stanley | | DIXON | BLUHM | 201,138 | 144,000 | 130,790 | 02/15/2007 | 06/30/2008 |
| 17669A | HHMI Bustamante Lab Modificati | Closeout | 90% | Stanley | | DIXON | BLUHM | 70,126 | 50,000 | 65,080 | 02/15/2007 | 07/31/2007 |
| 12309A | Northern Regional Library Faci | Construction | 5% | Northern Region | | SASAI | ZILBER | 619,000 | 0 | 233,385 | 09/01/2008 | 12/15/2008 |
| 17671A | The Scholars Workstation Reloc | Closeout | 99% | Hearst Fld A | | DELA | ZILBER | 398,000 | 137,855 | 390,477 | 03/01/2007 | 04/03/2007 |
| 17664A | University Hall Rooms 615A-D R | Closeout | 100% | University | | CHUNG | ZILBER | 110,000 | 40,000 | 53,424 | 04/09/2007 | 04/20/2007 |
| 18193B | Campbell Hall Pre-Schematics | Programming | 96% | Campbell | | ROSENTHAL | BLUHM | 300,000 | 0 | 683,188 | 10/01/2009 | 05/31/2012 |
| 17674A | AC units installation in room | Closeout | 80% | Doe Library | | ODA | ZILBER | 140,000 | 125,782 | 137,748 | 02/20/2008 | 03/30/2008 |
| 12316A | CKC Renewal Phase 1 - Building | Construction | 30% | |  | BOLTON | JOHNSON | 51,063,000 | 40,419,000 | 10,448,139 | 07/01/2008 | 06/30/2009 |
| 12316B | CKC Renewal Underground Utilit | Construction | 07% | Clark Kerr Camp | | TOWN | JOHNSON | 21,669,000 | 16,098,000 | 1,295,737 | 07/02/2008 | 05/31/2012 |
| 12292D | Warren Surge: Koshland Hall Rm | Closeout | 10% | Koshland | | FISH | BLUHM | 555,000 | 85,000 | 532,458 | 05/01/2007 | 04/01/2008 |
| 12304A | Inter Campus Comm. System (ICC | Construction | 80% | | | DANIELS | ZILBER | 1,025,000 | 694,500 | 819,924 | 05/26/2008 | 08/29/2008 |
| 17677A | Unit 3 Dining Common Steam Boi | Closeout | 99% | Rh3 Dining | | ODA | ZILBER | 200,000 | 0 | 128,325 | 06/15/2007 | 12/11/2007 |
| 12313B | LBNL Calvin Lab Casework | Construction | 90% | Calvin Lab | | FISH | ZILBER | 750,000 | 0 | 539,488 | 08/01/2007 | 03/14/2008 |
| 18534A | 2483 Hearst Avenue Acquisition | Study Only | % | | | HUFFERD | HATHEWAY | 29,000 | 0 | 11,666 | | |
| 12318A | Zellerbach - Mezzanine Restroo | Construction | 95% | Zellerbach |  | PETERSON | ZILBER | 800,000 | 634,100 | 591,317 | 07/09/2007 | 09/30/2008 |
| 12314A | Lawrence Berkeley National Lab | Design Development | 95% | CRT | | MARTINEZ | BLUHM | 112,944,000 | 88,316,000 | 4,772,734 | 01/01/2009 | 05/31/2011 |
| 12313A | Lawrence Berkeley National Lab | Design Development | 50% | Helios Research | | SWANSON | BLUHM | 198,246,000 | 153,750,000 | 10,326,939 | 07/15/2008 | |
| 12310A | Lawrence Berkeley National Lab | Concept | 100% | | | HALEY | BLUHM | 10,937,000 | 8,055,000 | 1,582,083 | 03/31/2008 | 06/30/2009 |
| 12321B | Bowles Hall Renovation Study | Study Only | 100% | Bowles --1230 | | MCGARRAHAN | ZILBER | 224,000 | 4,000 | 223,145 | 07/12/2007 | 02/12/2008 |
| 19347A | LBNL Calvin Lab Office Casewor | Construction | 100% | Calvin Lab | | FISH | ZILBER | 250,000 | 0 | 249,976 | 08/29/2007 | 02/01/2008 |
| 17681A | East Asian Library Donor Signa | Closeout | 75% | | | MATHERS | GAYLE | 325,000 | 270,000 | 225,246 | 08/01/2007 | 03/15/2008 |
| 18205A | Kroeber Hall, Hearst Museum Ad | Study Only | 0% | Kroeber | | PIATNITZA | MARTHINSEN | 130,000 | 0 | 101,479 | | |
| 18208A | Campus PV Solar Installation S | Study Only | 60% | Addison1950 | | CHESS | GAYLE | 36,000 | 0 | 14,007 | | 01/31/2008 |
| 12322A | University Village - Section A | Construction | 99% | |  | MAR | GAYLE | 3,310,000 | 0 | 2,499,533 | 07/25/2007 | 12/31/2007 |
| 19346A | Gill Tract Abandoned Buildings | Construction | 65% | Gill Tract Trac |  | ELLISEN | ZILBER | 938,000 | 0 | 222,043 | 08/30/2007 | 09/01/2009 |
| 18209A | Sather gate Safety & Structura | Study Only | 100% | Landscape - Cam | | HORNER | GAYLE | 50,000 | 0 | 50,775 | | |
| 12323B | Anna Head Site-Residence Halls | Study Only | 0% | | | PIATNITZA | MARTHINSEN | 750,000 | 20,000 | 25,866 | | |
| 17683A | Replace Hastings Reserve -Red | Bid/Award | 100% | | | ELLISEN | ZILBER | 173,100 | 133,100 | 68,003 | 08/04/2008 | |
| 12319A | Path of Travel Improvements - | Working Drawings | 80% | Landscape - Cam | | HORNER | GAYLE | 602,000 | 387,000 | 294,586 | 03/14/2008 | 06/26/2009 |
| 12326A | VLSB and Dwinelle Classroom Re | Construction | 85% | Dwinelle | | LEE | ZILBER | 1,000,000 | 800,000 | 446,566 | 01/01/2008 | 08/31/2008 |
| 17684A | University Hall Rm. 41 Renovat | Closeout | 99% | University | | CARAVES | ZILBER | 225,000 | 173,000 | 209,701 | 11/07/2007 | 01/22/2008 |
| 18212A | Bowles Hall Feasibility Study | Study Only | 100% | Bowles --1230 | | MCGARRAHAN | JOHNSON | 215,000 | 0 | 209,441 | 11/09/2007 | 02/29/2008 |
| 18213A | Stern Hall Study Update | Study Only | 100% | Stern | | MCGARRAHAN | JOHNSON | 186,640 | 0 | 183,289 | 10/31/2007 | 02/29/2008 |
| 19345A | RSF Gym Roof Replacement | Construction | 100% | | | ZYLLA | JOHNSON | 1,476,000 | 1,088,385 | 825,599 | 05/26/2008 | 09/19/2008 |
| 17686A | Evans Hall 7th Floor Renovatio | Construction | 100% | Evans | | ELLISEN | ZILBER | 390,000 | 176,692 | 348,925 | 06/16/2008 | |
| 12325A | Campus Building Accessibility | Construction | 85% | | | LEE | ZILBER | 500,000 | 350,000 | 347,959 | 03/24/2008 | 08/30/2008 |
| 12263B | Memorial Stadium Seismic Safet | Schematic Design | 75% | Stadium | | MAR | GAYLE | 1,000,000 | 0 | 181,199 | | |
| 17685A | Hass School of Business Room S | Construction | 99% | Haas Stu Bld | | ODA | ZILBER | 255,000 | 0 | 129,486 | 04/21/2008 | 07/18/2008 |
| 12329A | Lighting Step 6 -Integrated Li | Construction | 50% | Dwinelle | | LEE | ZILBER | 500,000 | 400,000 | 215,559 | 12/14/2007 | 01/30/2009 |
| 17710A | Stanley Hall HHMI Macro Lab B- | Closeout | 10% | Stanley | | GEE | ZILBER | 185,000 | 155,000 | 176,794 | 11/05/2007 | |
| 12240D | SAHPC Litigation Related Costs | Study Only | 75% | | | DIXON | GAYLE | 0 | 0 | 1,058,484 | | |
| 12240E | SAHPC Tree Removal Related Cos | Construction | 60% | | | DIXON | GAYLE | 411,000 | 351,000 | 375,258 | 11/08/2007 | 08/29/2008 |
| 12316C | CKC Renewal Phase 2 - Building | Working Drawings | 10% | | | BOLTON | JOHNSON | 55,240,000 | 42,936,000 | 508,081 | 06/30/2009 | |
| 12331A | Wheeler Rms 21-23 Assistive Te |