Project

Status

Budget

Construction

Project
Number
Title Phase Phase %
Complete
Bldg. Pic. Project
Manager
Assistant
Director
Project Const. Expenses
-to-date
Start Finish




02C2194Sudden Oak Death recharge expeProgramming80%Landscape - CamHORNERGAYLE23,500013,872
06C4612Contract management fee reimbuCloseout100%Botanical GardeCERNEYGAYLE006,206
06C4671Winter Creek Temporary RepairsCloseout18%Landscape - CamBOLTONJOHNSON136,00066,000127,22110/20/200605/31/2009
06C5002Donated funds for outdoor art Construction80%Landscape - CamHORNERGAYLE7,9324,93212,08402/01/200612/26/2009
06C5111AKJDAP Recharge (Labor Only)Concept%Addison1950LAWRENCEMARTHINSEN00302,969
07C5502Cloyne Court Inspection & ProjDesign Development80%Addison1950LEONYJOHNSON80,0000161,577
07C5642UNIT 3 CENTRAL REFRIGERATION UWorking Drawings10%Rh3 DiningGEEZILBER52,70022,00050,066
07C5717Do study of Moffitt Library utStudy Only95%MoffittGeeZILBER50,00035,00041,175
07C5760RAD Lab computer installation,Closeout100%Soda HallPIANCAZILBER94,000092,17105/21/2007
08C5945Ben Shemuel of Shen Milsom & WBid/Award80%Lawrence Hall oOWENSZILBER20,000019,126
08C6000Install 2 (e) 6 chem fume hoodConstruction90%StanleySASAIZILBER55,187041,90710/31/200809/30/2009
08C6070PRR for the replacement of exiConstruction90%CoryPIANCAZILBER99,00089,00093,32211/01/2007
08C6081Install new 3 acid wash chemicCloseout50%StanleyGeeZILBER67,00048,00037,003
08C6093Room B244 Stanley - install elCloseout50%StanleyGeeZILBER72,40049,00064,01001/28/2008
08C6107Law School Ventilation ProjectCloseout100%LawEllisenZILBER75,000075,93412/01/2008
08C6165RSSP 2610 CHANNING WAY - SERVEConstruction75%Channing 2612SASAIZILBER70,00054,00062,02012/21/200706/30/2008
08C6173CKC DINING BLDG 10 GARDEN ROOMConstruction98%Channing 2612FISH0026,250
08C6179Outdoor banner production and Construction80%Landscape - CamHORNERGAYLE68,00053,00061,15403/17/200809/12/2008
08C6181Campus beautification projectsConstruction90%Landscape - CamHORNERGAYLE2,9702,0002,58101/08/200812/26/2008
08C6215Unit Three Ida Sproul - elevatCloseout100%Rh3 SproulDANIELSZILBER100,00062,000100,47007/22/200801/13/2009
08C6242Bracing of existing bookshelveSchematic Design%Scanlin13,10007,667
08C6261renovation of Feng Wang lab, BConstruction10%BirgePIANCAZILBER50,00036,00038,46504/01/2008
08C6270LA LOMA BLDG 1 & 2 NW CORNER ACloseout100%Foothill HousinOWENSZILBER17,000014,547
08C6281For construction of a fire ratCloseout100%CoryPIANCAZILBER50,000048,35903/24/2008
08C6314UNIT 3 IDA SPROUL - REPAIRS TOCloseout100%Rh3 SproulOwensZILBER65,00030,00032,767
08C6334Run Low voltage cables from thCloseout100%Soda HallPIANCAZILBER27,00019,50026,48305/01/2008
08C6341B. CLEARY - DESIGN FOR DRY ROTCloseout100%ClearyOwensZILBER642,000506,000613,54812/22/200804/19/2009
08C6315CKC BLDGS 11, 12, 15, 16 & 17 Construction75%ELLISENZILBER70,0002,00077,24105/18/2009
08C6449Restripping of parking lot andConstruction10%MinorGeeZILBER24,00020,0004,169
08C6425Please install card access secCloseout100%Calvin LabFish46,000036,081
09C6500demo Birge B229Construction10%BirgePIANCAZILBER2,3002,00016,85408/04/2008
09C6509131A Stanley - install electriCloseout10%StanleyFISH40,00034,00029,840
09C6512Multi-Cultural Center/Heller FConstruction50%King UnionDELAJOHNSON76,00047,88135,35110/26/200912/04/2009
09C6514CUBS Credit Union to old PhotoSubstantial Completion100%King UnionDELAJOHNSON4,750018,60507/27/200908/21/2009
09C6516demolition, Birge B123Construction10%BirgePIANCAZILBER98,00090,00015,06608/18/2008
09C6526Birge B131 DemoConstruction10%BirgePIANCAZILBER68,00060,00027,29608/18/2008
09C6527Extend corridor HVAC, first flConstruction10%Le ContePIANCAZILBER98,00088,00097,65709/15/2008
09C6544Decontamination and decommissiStudy Only90%San Pablo 6701PETERSONZILBER205,0003,000108,69310/01/2009
09C6546Exterior signage to rename buiCloseout100%2151 Berkeley WHORNERGAYLE6,0004,0005,77101/15/2009
09C6539Design and construct temporaryCloseout95%2151 Berkeley WOWENSZILBER90,00070,00081,15210/06/200810/31/2008
09C6576Stanley B307D. Install susp.ceConstruction98%StanleyFISH89,00072,40072,785
09C6593The shower rooms in both the mConstruction30%Rec Sprt FacOwensZILBER149,00050058,05910/23/200901/15/2010
09C6598HVAC for Yildiz sound-proof roConstruction10%BirgePIANCAZILBER55,00050,00044,57310/13/2008
09C6601Replace existing wiring for MeBid/Award50%ZellerbachODAZILBER453,000350,000477,173
09C6604Provide directory and wayfindiConstruction60%Doe AnnexMARGAYLE90,000074,50202/01/200905/01/2009
09C6624Birge B125 HVACConstruction10%BirgePIANCAZILBER90,00080,00077,35311/03/2008
09C6628Le Conte 140 ceiling, fire sprConstruction10%Le ContePIANCAZILBER30,00025,00021,88811/10/2008
09C6633B207 Stanley-install electricaConstruction75%StanleyFishZILBER32,00022,50021,399
09C6667Haas School of Business ExteriCloseout80%Haas Stu BldDELAJOHNSON600,000541,600428,47006/01/200908/14/2009
09C6653Stanley B207 and B246. RelocatConstruction10%2151 Berkeley WPIANCAZILBER14,50014,5008,76505/18/2009
09C6693Installation of steel storage Working Drawings25%Edwards FldEllisenZILBER001,80602/02/2009
09C6701(1) quote/proposal to develop Concept75%SRB 1EllisenZILBER3,00002,310
09C6709The linoleum flooring is brokeBid/Award100%GianniniLEONYJOHNSON00516
09C6722Please coordinate installationConstruction95%Haas PavilionEllisenZILBER11,0008,5009,956
09C6724lighting study for LHS auditodBid/Award80%Lawrence Hall oOWENSZILBER17,350016,794
09C6725CKC bldg 16 Re-roofCloseout100%Clark Kerr CampCHUNGZILBER123,000104,000110,77205/25/200908/21/2009
09C6746RSSP Design Services: ArchitecWorking Drawings75%Rh3 DiningODAZILBER316,560125,000291,16005/25/200909/25/2009
09C6755prr to study the addition air Working Drawings10%CoryPIANCAZILBER35,00025,00030,46605/25/2009
09C6757Planning process for packer trProgramming20%Carlton2000FungJOHNSON10,00008,275
09C6769Foothill loading dock - repairCloseout100%Foothill HousinDELAJOHNSON36,00031,90035,16307/20/200908/07/2009
09C6789Provide a planning and design Working Drawings95%DavisFeherBLUHM70,00050,000009/01/200910/23/2009
09C6790proceed w/front end work needeCloseout50%Rec Sprt FacOwensZILBER7,00007,14809/14/2009
09C6780Estimate to remove Campus LinkConstruction80%King UnionPETERSONZILBER8,00007,98708/05/200908/21/2009
09C6781Beverly Clear South Womens rooWorking Drawings0%ClearyDELAJOHNSON110,50064,03134,47012/01/200901/15/2010
09C6796Update Builders of Berkeley WaSubstantial Completion75%%Doe LibraryHORNER12,00010,0008,10309/03/200909/04/2009
09C6797Located in Dwinelle Plaza, worCloseout100%DwinelleHORNERGAYLE12,00011,00011,66608/20/200908/22/2009
09C6802Install Fire Sprinkler and relConstruction50%LewisFish17,3751,2401,928
09C6804Replace damaged door in rm. 17Construction10%CoryPIANCAZILBER15,00010,2007,52206/01/2009
09C6819PRR for the modification and eConstruction10%CoryPIANCAZILBER10,0007,00014,80606/15/2009
09C6832Paragon CO#3 $11,039.00 Add. RCloseout100%LewisFish18,74418,34419,271
09C6833Paragon Mechanical CO#1 $5,393Closeout100%LewisFish19,29418,89419,422
09C6839STUDENT SVCS BLDG INTERIOR PAIBid/Award0%Haas Stu BldCARAVES23,50022,75023,236
09C6841Bldg 25 Wheelchair RampConstruction100%Clark Kerr CampHORNERGAYLE1,1950009/07/200909/10/2009
09C6843complete work needed to hook uCloseout40%Rec Sprt FacOwensZILBER31,00030,00028,146
09C6844Reface Lockers in Football locConstruction70%StadiumPETERSONZILBER24,0006,40019,725
09C6845Removal of soil from South sidConstruction%Richmond Field FungJOHNSON6,7000006/20/2009
09C6850Please open a new PRR for the Closeout100%King UnionDELAJOHNSON20,00015,00029,52107/20/200908/25/2009
09C6851Please remodel basement of MLKWorking Drawings65%King UnionDELAJOHNSON5,00001,613
10C6861Sutradja Dai Hall - Purchase/IConstruction99%DavisFeherBLUHM58,00055,000007/01/200908/21/2009
10C6862Please use a general contractoConstruction90%EshlemanPETERSONZILBER17,0003,60019,57108/03/200909/15/2009
10C6891Please install new building siConstruction0%King UnionPETERSONZILBER8,5007,50077408/03/200908/20/2009
10C6892Please investigate expanding tFeasibility0%ChavezPETERSONZILBER00258
10C68934th floor meeting room wall reConstruction50%King UnionPETERSONZILBER55,00050,00048,61408/10/200908/23/2009
10C6901Sutardja Dia Hall (CANN# 1152)Schematic Design70%DavisFeherBLUHM70,00050,000008/31/2009
10C6902Steel cable rail at bottom of Study Only0%2151 Berkeley WPETERSONZILBER000
10C6906Lab cabinetry installation & oConstruction10%Hearst MinPIANCAZILBER50,000030108/17/2009
10C6907location: Hearst Mining Rm. 14Construction25%Hearst MinPIANCAZILBER35,00030,00030108/17/2009
10C6909Relocate (e) 120V to approx 80Feasibility50%StanleyFish00129
10C6910PRR for condenser pipe repair Construction25%CoryPIANCAZILBER10,0007,00023708/17/2009
10C6921Remove carpet in room 112 and Construction10%WursterPETERSON30,00025,00038708/20/200909/11/2009
10C6923American Air fit-up work for tConstruction10%Calvin LabPIANCAZILBER3,5002,90012909/14/2009
10C6925Install new AV system in Room Design Development10%WursterPETERSONZILBER17,00012,00014,935
10C6930Office Renovation at 2240 PiedBid/Award0%Piedmont2240PETERSONZILBER15,00012,0000
10C6931Sutardja Dai Hall (CAAN 1152) Design Development50%DavisFeherBLUHM7,0005,000010/26/200912/24/2009
10C6932Authorize installation for an Construction100%King UnionPETERSONZILBER5,0003,5003,92108/20/200909/11/2009
10C6938Need to provide a circuit for Closeout1000%King UnionDELAJOHNSON2,5001,982599
10C6941Remove existing temporary offiConstruction35%Haas PavilionOwensZILBER35,00030,000878
10C6942Need an estimate to clean up tFeasibility0%EshlemanPETERSONZILBER2,5001,500159
10C6943Install 12-15 banner on CampusCloseout100%Landscape - CamHORNERGAYLE3,2752,8743,43409/23/200909/23/2009
10C6947Increase size of door opening Construction100%Rec Sprt FacOwensZILBER35,00031,00032,88009/21/200910/02/2009
10C6956G93 Tolman - Contract support Construction90%TolmanDELAJOHNSON25,10020,35015,21509/28/200911/13/2009
10C6958Please modify existing computeConstruction90%Calvin LabPIANCAZILBER1,00060076609/16/2009
10C6963Install 12 high-bay 6 lamp T5HConstruction80%Rec Sprt FacOwensZILBER32,00029,00030,153
10C6967ST Hall bathroomCloseout100%SternDELAJOHNSON5,50005,34708/18/200909/01/2009
10C6968We plan to install fundraisingCloseout100%Haas Stu BldHORNERGAYLE3,0002,3703,01109/30/200909/30/2009
10C6970Please coordinate installationConstruction90%Rec Sprt FacOwensZILBER16,00014,30014,202
10C6971Repair walls and floor in roomFeasibility0%2151 Berkeley WPETERSONZILBER5,00000
10C6982Ellen Owens said she d take thConstruction90%Rec Sprt FacOWENSZILBER27,00022,00024,13810/05/2009
10C6984Install 2 automatic doors and Working Drawings0%Faculty ClubPETERSONZILBER10,0006,0002,53710/26/200912/01/2009
10C6985Contract to repair dry rot to Bid/Award75%Foothill HousinFish50,00040,0001,429
10C6974Demolition /remodeling room 12Construction5%2151 Berkeley WPETERSONZILBER12,0009,00045110/05/2009
10C6998John has already investigated Bid/Award10%2151 Berkeley WPIANCAZILBER25,00021,00065512/01/2009
10C6999Unit 1 & 2 Res. Hall exterior Construction45%Rh1 CheneyOwensZILBER20,000090910/01/200912/11/2009
10C7002Morgan 250 - Remove originaol Closeout100%MorganEllisenZILBER22,00018,000193
10C7005PRR for rm. 173, cory hall, stStudy Only10%CoryPIANCAZILBER2,0000010/29/2009
10C7007Please coordinate installationBid/Award50%Haas PavilionOwensZILBER3,0002,6000
10C7022Lint recovery system for laundBid/Award10%Rec Sprt FacEllisenZILBER8,0007,6000
10C7037CKC Bldg 12 Security screens iBid/Award5%Clark Kerr CampMAYOJOHNSON14,00011,000002/12/2010